Back to section
Regulácie 🔥 Top

New York becomes first state to impose a data center moratorium

Streda 15. júla 2026 Source: Washington Post

What happened

New York Governor Kathy Hochul signed an executive order on July 14, 2026 imposing a moratorium on new hyperscale data center construction over 50 MW — the first such statewide action in US history.

Context and impact

The state is pausing discretionary environmental permits for up to one year while the Department of Public Service develops a Generic Environmental Impact Statement for data centers. The order directly affects Microsoft, Google, Amazon, and Meta expansion plans in the state. The AI industry fears a domino effect as other states consider similar measures before elections.

Details

  • Moratorium lasts up to 12 months from signing
  • Applies to facilities with electrical demand of 50 MW or more
  • DEC will not issue discretionary permits during GEIS development
  • Goal: protect ratepayers from rising energy costs driven by AI infrastructure
  • New York is the first US state to impose such a broad moratorium
  • DIGIT Office gains authority to oversee safety measures of frontier AI developers
Open original source Washington Post