New York Governor Kathy Hochul signed an executive order on July 14, 2026 imposing a moratorium on new hyperscale data center construction over 50 MW — the first such statewide action in US history.
Context and impact
The state is pausing discretionary environmental permits for up to one year while the Department of Public Service develops a Generic Environmental Impact Statement for data centers. The order directly affects Microsoft, Google, Amazon, and Meta expansion plans in the state. The AI industry fears a domino effect as other states consider similar measures before elections.
Details
- Moratorium lasts up to 12 months from signing
- Applies to facilities with electrical demand of 50 MW or more
- DEC will not issue discretionary permits during GEIS development
- Goal: protect ratepayers from rising energy costs driven by AI infrastructure
- New York is the first US state to impose such a broad moratorium
- DIGIT Office gains authority to oversee safety measures of frontier AI developers